Current Projects

2015-03-CP-Public-Works-8188-landing-page-banner

2020 Pavement Rehabilitation Project

The 2020 Pavement Rehabilitation Project is began June 8 and expected to be complete by November 2020, weather and dynamics permitted. The improvement project employs different rehabilitation and reconstruction methodologies to 42 roads throughout the City.

Download the projected schedule for the 2020 Pavement Rehabilitation Project with a list of dates, all eight areas, and streets.

Download a diagram of the areas scheduled for construction and a map with color-coded streets identifying the pavement plan.

Bookmark this map to quickly learn the progress of this project.

2020 Pavement Rehabilitation Project

The schedule below is subject to change due to traffic incidents, weather, availability of equipment, materials, and/or construction-related issues. During the construction, please observe all regulatory signage and instructions.

Update: August 10, 2020

Monday – August 10th
Concrete Removal and Replacement – Vacquero Drive
Asphalt Paving – Stonemont Drive & Stonedale Drive
Asphalt Patching – Campden Place raising manholes
Asphalt Milling – None
Subgrade preparation (Dirt work) – Shady Oak Lane & Glen Oaks

Tuesday – August 11th
Concrete Removal and Replacement – Vacquero Drive
Asphalt Paving – Briar Haven Court, Briar Trace Court and Campden Place
Asphalt Patching – High Ridge Way
Asphalt Milling – None
Subgrade preparation (Dirt work) – Shady Oak Lane & Glen Oaks

Wednesday – August 12th
Concrete Removal and Replacement – Vacquero Drive
Asphalt Paving – None
Asphalt Patching – High Ridge Way & Claymour Court
Asphalt Milling – None
Subgrade preparation (Dirt work) – Shady Oak Lane & Glen Oaks

Thursday – August 13th
Concrete Removal and Replacement – Vacquero Drive
Asphalt Paving – None
Asphalt Patching – Claymour Court
Asphalt Milling – None
Subgrade preparation (Dirt work) – Shady Oak Lane & Glen Oaks

Friday – August 14th
Concrete Removal and Replacement – Backfill and restoration at previously poured locations
Asphalt Paving – None
Asphalt Milling – None
Subgrade preparation (Dirt work) – Shady Oak Lane & Glen Oaks

Update: August 5, 2020

From August 5 – 11, contractors will be working on the streets listed below. During the construction, please observe all regulatory signage and instructions.

Wednesday – August 5th
Concrete Removal and Replacement -Stonemont Drive & Stone Dale Drive
Asphalt Paving – Exeter Drive & Shoreham Circle
Asphalt Patching – Berganot Trail
Pothole Repair – Castle Pines Parkway and Shoreham Drive
Subgrade preparation (Dirt work) – Vaquero Drive

Thursday – August 6th
Concrete Removal and Replacement – Briar Haven Court & Briar Trace Court
Asphalt Paving – Vaquero Drive
Asphalt Patching – Brambleridge Drive
Pothole Repair – Castle Pines Parkway & Shoreham Drive
Asphalt Milling – Shady Oak Lane
Subgrade preparation (Dirt work) – Shady Oak Lane

Friday – August 7th
Concrete Removal and Replacement – Backfill and restoration at previously poured locations
Pothole repair – Castle Pines Parkway and Shoreham Drive
Asphalt Milling – Glen Oaks Avenue / Briar Haven Court & Briar Trace Ct.
Subgrade preparation (Dirt work) – Shady Oak Lane

Monday – August 10th
Concrete Removal and Replacement – Vaquero Drive
Asphalt Paving – Stonemont Drive & Stonedale Drive
Asphalt Patching – None
Subgrade preparation (Dirt work) – Shady Oak Lane

Tuesday – August 11th
Concrete Removal and Replacement – Vaquero Drive
Asphalt Paving – Briar Haven Ct & Briar Trace Court
Asphalt Patching – Brambleridge Drive
Subgrade preparation (Dirt work) – Vaquero Drive

Thank you for your patience as we continue to work on improving our infrastructure. If you have any questions, please call 720-646-0346, 303-660-0439, or email Public Works at PWRequests@castlepinesco.gov


Update: July 31, 2020

The City of Castle Pines is on schedule with its 2020 Pavement Rehabilitation Project, which began in June and is expected to be complete by November 2020.

The 2020 Pavement Rehabilitation Project includes the rehabilitation and/or reconstruction of 42 sections of the roads, including curb and gutters, sidewalks and ADA-compliant curb ramps to restore the City’s 37 miles of roadways. For the latest information on the project, visit the City’s interactive map.

Next week, August 3 – 7, contractors will be working on the streets listed below. During the construction, please observe all regulatory signage and instructions. At this time, streets and roads will remain open to traffic.

 

Monday – August 3rd

Concrete Removal and Replacement – Stonemont Drive & Stone Dale Drive

Asphalt Paving – Deer Clover Way & Raven Court

Asphalt Patching – Cotton Grass Court

Subgrade preparation (Dirt work) – Vacquero Drive

 

Tuesday – August 4th

Concrete Removal and Replacement – Stonemont Drive & Stone Dale Drive

Asphalt Paving – Manchester Court & Exeter Drive & Exeter Court

Asphalt Patching – Berganot Trail

Subgrade preparation (Dirt work) – Vacquero Drive

 

Wednesday – August 5th

Concrete Removal and Replacement -Stonemont Drive & Stone Dale Drive

Asphalt Paving – Exeter Drive & Shoreham Circle

Asphalt Patching – Berganot Trail

Pothole Repair – Castle Pines Parkway and Shoreham Drive

Subgrade preparation (Dirt work) – Vacquero Dr

 

Thursday – August 6th

Concrete Removal and Replacement – Briar Haven Court & Briar Trace Court

Asphalt Paving – Vaquero Drive

Asphalt Patching – Brambleridge Drive

Pothole Repair – Castle Pines Parkway & Shoreham Dr

Asphalt Milling – Shady Oak Lane

Subgrade preparation (Dirt work) – Shady Oak Lane

 

Friday – August 7th

Concrete Removal and Replacement – Backfill and restoration at previously poured locations

Pothole repair – Castle Pines Parkway and Shoreham Drive

Asphalt Milling – Glen Oaks Avenue

Subgrade preparation (Dirt work) – Shady Oak Lane

 

Thank you for your patience as we continue to work on improving our infrastructure. If you have any questions, please call 720-646-0346, 303-660-0439 or email Public Works at PWRequests@castlepinesco.gov