To continue supporting the growth on the east side of Castle Pines, North Canyons Development Company is working to realign the current S. Havana Street several hundred feet to the east. South Havana Street will remain open during the construction of the new alignment, with minimal traffic impacts anticipated.

The new alignment of the roadway will provide several benefits to the traveling public, including:

  • Moving the roadway to align with the roadway network of the future mixed-use area, south of Castle Pines Parkway and east of I-25.
  • Reducing the total number of intersections along Castle Pines Parkway and improving traffic efficiency.
  • Adding a traffic signal at the newly aligned intersection to improve safety and access.

North Canyons Development Company will pay for and construct this project. Douglas County will also contribute $500,000. The City will review permits and inspect the infrastructure before the realigned roadway is accepted as a City-owned asset.

Anticipated Schedule

  • Project Start Date: May 2025
  • New Havana Alignment Opens: Early Summer 2026
  • Old Havana Alignment Demolished: Summer 2026