Crews are currently working on final construction activities (lane striping, etc.) on the Phase One portion of the Monarch Boulevard reconstruction project. Phase One, between Berganot Trail and Hidden Pointe Boulevard, is scheduled to reopen to local traffic on Tuesday, August 12. Crews will then begin work on Phase Two, between Hidden Pointe Boulevard and Buffalo Trail.
Phase Two will also include initial work on the roundabout to be constructed at the Monarch Boulevard and Buffalo Trail intersection. This initial roundabout work will occur outside travel lanes and will not impact traffic traveling through the intersection via the Buffalo Trail detour.
Monarch Boulevard Reconstruction Phasing Overview:
- Phase One: Berganot Trail to Hidden Pointe Boulevard - Complete August 12
- Phase Two: Hidden Pointe Boulevard to Buffalo Trail will be reconstructed. The side of the new roundabout adjacent to Coyote Ridge Park will be built outside of existing travel lanes. - Begins August 12; Scheduled to be completed in late September/early October.
- Phase Three: The remaining portion of the roundabout will be constructed. Note: Northbound and southbound traffic will be open on the entirety of Monarch Boulevard during Phase Three. When Monarch Boulevard reopens, Buffalo Trail will be temporarily closed during this phase to finish construction of the new roundabout. - Will begin after Phase Two is complete; Anticipated to be completed in late October/early November.
What to Expect During Phase Two:
- During Phase Two of Monarch Boulevard Reconstruction, access to Hidden Pointe Boulevard will be maintained to local traffic and emergency services from the south side of the intersection at Monarch Boulevard.
- Construction activities will begin for the side of the roundabout next to Coyote Ridge Park.
Closure and Detour Information:
- Beginning August 12, Monarch Boulevard will be closed to through traffic from the north side of the Hidden Pointe Boulevard intersection to Buffalo Trail.
- Two-way traffic will be maintained on Monarch Boulevard, south of the Hidden Pointe intersection, for local neighborhood traffic. This closure is necessary to ensure the safety of construction crews and drivers. Detour routes will be clearly marked to minimize inconvenience.
We recognize the impact of construction on your daily routines and are committed to completing this project as swiftly as possible. For detailed information, including detour routes and project updates, please visit our website at www.CastlePinesCO.gov/Monarch.
If you have any questions or need additional assistance, please contact us at monarch@castlepinesco.gov or call 303-705-0200. Thank you for your patience as we work to create safer and more efficient roadways in Castle Pines.